JLF were recently involved in a project encompassing site wide civil engineering works at the Greencore factory site in Warrington. Works were required to enable Greencore to proceed with a new water treatment facility which will assist with the production of their food products.

 

The project comprised of the following items:

 

  • Demolition and removal of existing infrastructure including steelwork pipe gantries, masonry buildings, and acoustic cladding panelling.
  • Construction of new reinforced concrete slabs to support 40 tonne storage tanks.
  • Installation of new surface water drainage.
  • Construction of new blockwork to support pipework.
  • Below ground drainage connections.
  • Installation of new roofing to retained outbuildings.
Project Duration

3 Months

Project Cost

£150k

Project Completion

June 2020